This update is full of information on the next phase of construction likely scheduled to begin in July and run through October. Major aspects include:
- Remove dike in its entirety to connect tidal waters and fish from Port Susan, Skagit Bay and old channel of the Stillaguamish River
- Remove Eide Road
- Construct new 0.7 mile long wave protection berm to protect the City of Stanwood
- Construct new parking area near Hwy. 532 that connects to the new berm
- Build trail for pedestrian access on top of the new berm
- Build new short trail leading to channel connecting Davis Slough for non-motorized boats
- Excavate additional channels and lower areas on the site
For more information contact Loren Brokaw at Loren.Brokaw@dfw.wa.gov.